Guide for Engineer ---How to design manufacturing Lines June 11, 2012 revision 6122
CONTENTS
@ Don’t show off your lines
A Which is the best
B What is important?
C Engineer’s Disposition
D Motion study
Some competitor companies may want to know your manufacturing methods. Even your customers may try to steal your factory methods and may inform your competitor’s company. I have some experience with a famous electric appearance manufacturing company that stole some information when they visited our factory as an auditor.
You should seal the parts of machine where you think having important technological method.
I like to see manufacturing plant. In most cases,there are many hints to design machines and work spaces.
Some of them might not be so useful. But I used to get, at least, two or more technological hints at one site.
I always think that a line has many treasures!
Which is the best manufacturing system
I think that there is no best
system. Systems should be designed by considering their product’s feature.
Canon Corp. is famous for its manufacturing system called “cell production”.
They abolished their belt conveyed manufacturing lines. Instead of
their conveyor, they let their individual workers assemble all
processes by one worker. Some people say that it is the best way
to make the best of Japanese workers’ power. But I don’t think so.
Some time, it is correct but some time, it is incorrect.
If the life time of the product is as long as five or six months, the line
using conveyor may be best.
Under the“cell production”system, workers often require to be trained
in all processes of lines. So, it takes time till they make up their
manufacturing line to become well operated.
There is another factor to be considered. Quantity of daily product
will decide the style of the line, too.
Lines with belt conveyors will be good for
6 seconds to 30 seconds of its manufacturing cycle. It will be 900 to 4200 units
of product per 8 hours.
But cell production line has more flexibility in their capacity. The number of workers can be changed immediately. It is one of the strong points that cell production lines have. You can do same in lines with belt conveyor by increasing or decreasing the number of lines. But ,it may take some time.
I think most important thing to be considered is that managers or workers
can find easily any troubles occurring in those lines . “Just in time
system “ are well known in TOYOTA motors manufacturing. If there are any
troubles, the line will stop soon.
A line can be continued when each process has a stock of a certain amount of semimanufactured goods.
However, discovery of a trouble may be overdue and a damage may become large.
As a result, much time may be needed for restoration of the trouble which occurred.
I used to settle lines that their starting point close to the ending
point.
So, a worker can find the difference between input and output. It’s
one method for finding the problem of a production line.
If you have some to manage people who design machinery you should rule
them by the standard of machinery of your company lines. Many times
engineers might hate restrictions But you should determine the rule with
considering their opinions.
Considering is different from accepting their claims. You should decide the rule by yourself. The line should be designed using a certain doctrine.
I had aimed to establish efficient manufacturing lines where human resources are esteemed.
It’s necessary to use worker’s power effectively.
Only poor profits can be yielded when manufacturing efficiency falls. One
of reasons is that there are some waiting times occurred.
In many case you might not be able to find out the waiting time. The workers
tend to work according to the cycle time of the line. So, the standard labor
time should be estimated by using the P.T.S. (Predetermined Time Standard) I
used to determine the time by using R.W.F. (Ready Work Factor) that is one of
P.T.S. methods.
Some room time should be added to the result.
By the added time can be compared with the cycle time of the line. Then
you can judge whether there is waiting time or not.
But before this you should consider those motions of workers.
I also have been interested in method engineering. The method engineering is
the study of workers motion.
By the result, I can choose best way of manufacturing.
But, recently manufacturing are often done by machinery instead of workers.
I think in many factories there are lots of waiting delays in machine
movements. Therefore, we should remove such waiting times and then the
cycle time of machine will shorten. Some mechanical engineer may not be
able to find such waiting times, without knowledge of the motion study.
Using video recorder, you might find some problems of machinery movement.
To be continued!